Quadralets :
Work Under Construction
at
Laburnum Lane
November 2006
Quadralet Progress -
Group 5
External plaster including roofing tile work complete. Commencement of internal finishing.
Group 4
Commencement of external plasterwork.
Group 3
Internal plasterwork nearing completion.
Group 2
Brickwork complete. Internal plaster to commence Dec 11th.
Group 1
RCC work -2nd slab work in progress.
Row Houses
B05 - B04 - B03 - Brickwork complete and internal plaster commenced
2 slab complete of all Row houses